July 5, 2013
July 3, 2013
July 1 & 2, 2013
June 26, 27, & 28, 2013
June 25, 2013
June 24, 2013
June 22, 2013
June 21, 2013
June 19, 2013
June 17, 2013
June 11, 2013
June 10, 2013
June 07, 2013
June 05, 2013
June 04, 2013
June 03, 2013
- Day 11 - Forms Removed, Egress Window Well Installed, Waterproofing applied, and Sewer and Water Rough-Ins
May 30, 2013
May 28, 2013
May 26, 2013
- Eight and ninth change order submitted (Item missing from Pre-Construstion list, and what looks to be a RH waiver agreeing to move forward with the house despite the poorly represented lot grading)
May 21, 2013
May 17, 2013
May 16, 2013
May 14, 2013
- Our first delivery - Egress window and well
- Made our Seventh and final Change Order (I hope!)
- Our Lot (47) Staked
May 08, 2013
May 06, 2013
- Scheduled follow-up appointment with Rite Rug for Wednesday, May 08
- Last Ditch Effort to change elevation or exterior brick to stone because of houses behind our Lot - Denied :(
- Made our Fifth and Sixth Change Orders
- Met our PM for the first time - ran into him at the Model
- NVRM contacted us for more documents - Still no word on whether or not we're in underwriting or where we stand
April 20, 2013
- Submitted Address Marker Request to Google Maps
- Deadline for All Change Orders
- Contacted Guardian to remove and add items
- Attended our appointment for more document signing and quick look at model home for additional selections made
- Made our Third and Fourth Change Orders (Pending 1 more for Guardian, forgotten item, and extra outlets)
- Scheduled appointment with Ryan Homes for Friday, April 19
- NVRM Contacted us for followup documents
- Deadline for Structure Change Orders
- Second Change Order (A few outstanding non-standard requests)
- Attended our appointment with Ryan Homes - Made Exterior Color Selections
- First peek at the official floor plans - very small scale
- Made our First Change Order
- Visited Florence Model Home - Reviewed some options, furniture ideas
- Scheduled appointment with Ryan Homes for Saturday, March 30
- Our Big Book of Questions E-mailed to RH for preparation of next steps in process - Some questions already answered
- Attended our appointment with Guardian - Made our wiring/networking/security selections
- Attended our appointment with Rite Rug - Made our flooring selections
March 25, 2013
- Scheduled appointment with Rite Rug for Wednesday, March 27
- Received copy of the Ryan Homes Ratified Contract by e-mail
- Scheduled appointment with Guardian Home Technologies for Wednesday, March 27
- Got our BRAND NEW STREET ADDRESS - We're no longer just a lot!
- Scheduled appointment with NVRM for Tuesday, March 26
- Received a copy of the HOA documents
- Meet with the Sales Representative, Elizabeth, for Purchase Agreement Paperwork and partial payment of Good Faith Deposit - Placed our SOLD sign on our lot
- Made our first Change - Not an official change order
March 16, 2013
- Meet with the Sales Representative, Elizabeth, for Pre-Qualification - Reserved our Homesite
- Call to Ryan Homes regarding Home Of The Month Flyer - Scheduled an appointment to meet SR
- Visit to our first Ryan Homes Model - The Venice